Job: Shalvey Alteration
( Seperation Bathroom and Ensuit)
-
Construct New wall between ensuit and bathroom.
-
Install New windows , door frames and sliding door
-
Installation of Bathtub
-
Installation of sheetings
-
Installation of waterproof floor , wall and joint.
-
Installation of Floor and Wall tiles
-
Installatioin of basin , toilet and shower fittings
Duration: 1 week to 1.5 weeks.